May not look like much, but they've completed most of the removals and installed nearly all the curb. This all takes a fair amount of work, and once complete, sets the stage for the good stuff that's coming.

nice straight curb, they did a pretty good job on these. you can see it is pre-cored for the fenceposts.

curb crew hard at work

remember those ugly bleachers from the previous post? this is all that's left. The plywood box contains the electricals and have been weatherproofed. At first they tried removing this with a handheld jackhammer... after a day of that and getting almost nowhere through the thick concrete, they got a big jackhammer that connects to a backhoe. Then it was like cutting through butter.
Overall they're a little behind schedule at this point but I am not worried yet. They're working hard to get back on track. Stay tuned to see how it turns out.